Landscaping change order template

A guide from Scrivell ·

A free change order form for landscaping jobs. Print it from this page or download the PDF, keep a few in every truck, and use it whenever a job changes once the crew is on site. Below the form: what each part is for, a filled-in example, and how to make it stick.

Download the PDF

The blank template

Change order

Your company name · phone · email

No.
 
Date
 
Customer
Property address
Phone or email
Original estimate or contract no.
Crew lead
Prepared by

The change: what is added, removed or different

Why

☐ Customer request   ☐ Site conditions   ☐ Other: ____________________

Qty Unit Description Rate Amount
Crew hours
Materials
Equipment, disposal and other
Subtotal
Tax
Total for this change

Effect on schedule: ☐ None   ☐ Adds ____ day(s)

Customer approval

I approve the change described above and the added cost.

Customer name

Signature

Date

Not signed on site? Record how it was approved: ☐ Text ☐ Email ☐ Phone ☐ In person, and keep the message.

Office use: added to invoice no. ________ on ________ by ____

Letter size, one page. Free to use and change for your own business.

When to write a change order

Write one whenever the job changes in a way that affects the price, the scope or the schedule: the customer asks for more, swaps a material, or the site turns out different from what you quoted. Set a threshold that suits your business. Many owners write a formal change order for anything over a set amount, and simply record smaller extras with the job.

Small extras still need recording. Our guide on tracking extra work on landscaping jobs covers a simple routine for those.

What each part of the form is for

Number and date
Number change orders in sequence (CO-001, CO-002) so the office can see at a glance if one is missing.
Customer, property and contact
Enough to match the form to the right job without guessing.
Original estimate or contract number
Ties the change to the work it modifies, so it’s billed on top of the agreed price, not lost inside it.
The change, and why
One or two plain sentences. Ticking “customer request” or “site conditions” settles most disputes before they start.
Crew hours, materials and other costs
Quantities in the units your crew uses: hours, each, yards, tonnes. Group them the way you price them, so the office can copy lines straight onto the invoice.
Totals and tax
The price of this change on its own. The customer should see exactly what the extra costs.
Effect on schedule
Even “none” is worth writing down. If the change adds days, now is the time to say so.
Customer approval
A signature is best. If the customer agrees by text, email or phone instead, record how and when, and keep the message.
Office use
Where the change was billed. It closes the loop, so nothing is billed twice or missed.

A filled-in example

A customer asks for a paver edge along the front bed while the crew is on site. The crew lead fills in the form, prices it from the company’s rates, and the customer approves it by text. Names, numbers and prices are made up.

Change order

Example Landscape Co. · (555) 010-0142

No.
CO-014 
Date
2026-10-14 
Customer
J. Williams
Property address
12 Maple Crescent
Phone or email
(555) 010-0187
Original estimate or contract no.
EST-2026-031
Crew lead
Mike
Prepared by
Mike

The change: what is added, removed or different

Add a paver edge along the front bed (32 stones), set on screenings over landscape fabric.

Why

☒ Customer request, asked on site

Qty Unit Description Rate Amount
Crew hours
4hrCrew lead$65.00$260.00
4hrCrew member$50.00$200.00
Materials
32eaPaver edge stone, straight$9.50$304.00
0.5ydLimestone screenings$70.00$35.00
1rollLandscape fabric, 3 × 50 ft$28.00$28.00
Equipment, disposal and other
1loadDisposal of removed sod$40.00$40.00
Subtotal $867.00
Tax (13%)$112.71
Total for this change $979.71

Effect on schedule:None, done the same day

Customer approval

I approve the change described above and the added cost.

J. Williams

Customer name

Approved by text, 1:42 PM (saved)

Signature

2026-10-14

Date

Not signed on site? Record how it was approved: ☐ Text ☐ Email ☐ Phone ☐ In person, and keep the message.

Office use: added to invoice no. ________ on ________ by ____

Tips for using it on site

  1. 01Keep a pad in every truck

    A change order nobody can find on site doesn’t get written. Print a stack, or keep the PDF on the crew lead’s phone.

  2. 02Write it before the work, when you can

    Agreeing the price first is easier than collecting it afterwards. If you can’t price it on the spot, agree the rates and write down the quantities as you go.

  3. 03One change per form

    Two changes on one sheet are hard to approve, bill or dispute separately.

  4. 04Photograph the signed form

    Send the photo to the office the same day, and give the customer a copy.

  5. 05Bill it while it’s fresh

    The office adds each change order to the invoice and fills in the office-use line. Once a week, check for any numbers that never reached billing.

Where Scrivell fits

A paper form works when someone remembers to fill it in. Often the details are said out loud instead, in a voice memo or a text to the office. Scrivell catches those. Crews text a dedicated Scrivell number, and a message about extra work becomes a change order record with the work added, the materials and quantities, the price if one was stated, and whether the customer agreed. Hours become labor logs, and a receipt photo becomes a materials purchase.

What the office sees · example

Williams backyard

Voice memo · 1:38 PM

Needs review

“Williams place. Customer wants a paver edge along the front bed, thirty-two stones. Homeowner okayed it.”

Change order · Williams

  • + Paver edge, front bed
  • 32 edge stones
  • Customer agreed

The office confirms or edits the record, then uses it to fill in the change order or the invoice. Scrivell doesn’t produce this form, collect signatures or send invoices: it makes sure the change reaches the office with the details intact, and flags it when it isn’t clear the customer agreed.

See how it works for landscaping companies.

Catch the changes nobody writes down

Send a crew voice memo through the demo and see the change order the office gets, ready to confirm.