Landscaping change order template
A guide from Scrivell ·
A free change order form for landscaping jobs. Print it from this page or download the PDF, keep a few in every truck, and use it whenever a job changes once the crew is on site. Below the form: what each part is for, a filled-in example, and how to make it stick.
The blank template
Change order
Your company name · phone · email
- No.
- Date
- Customer
- Property address
- Phone or email
- Original estimate or contract no.
- Crew lead
- Prepared by
The change: what is added, removed or different
Why
☐ Customer request ☐ Site conditions ☐ Other: ____________________
| Qty | Unit | Description | Rate | Amount |
|---|---|---|---|---|
| Crew hours | ||||
| Materials | ||||
| Equipment, disposal and other | ||||
| Subtotal | ||||
| Tax | ||||
| Total for this change | ||||
Effect on schedule: ☐ None ☐ Adds ____ day(s)
Customer approval
I approve the change described above and the added cost.
Customer name
Signature
Date
Not signed on site? Record how it was approved: ☐ Text ☐ Email ☐ Phone ☐ In person, and keep the message.
Office use: added to invoice no. ________ on ________ by ____
Free template from scrivell.com
Letter size, one page. Free to use and change for your own business.
When to write a change order
Write one whenever the job changes in a way that affects the price, the scope or the schedule: the customer asks for more, swaps a material, or the site turns out different from what you quoted. Set a threshold that suits your business. Many owners write a formal change order for anything over a set amount, and simply record smaller extras with the job.
Small extras still need recording. Our guide on tracking extra work on landscaping jobs covers a simple routine for those.
What each part of the form is for
- Number and date
- Number change orders in sequence (CO-001, CO-002) so the office can see at a glance if one is missing.
- Customer, property and contact
- Enough to match the form to the right job without guessing.
- Original estimate or contract number
- Ties the change to the work it modifies, so it’s billed on top of the agreed price, not lost inside it.
- The change, and why
- One or two plain sentences. Ticking “customer request” or “site conditions” settles most disputes before they start.
- Crew hours, materials and other costs
- Quantities in the units your crew uses: hours, each, yards, tonnes. Group them the way you price them, so the office can copy lines straight onto the invoice.
- Totals and tax
- The price of this change on its own. The customer should see exactly what the extra costs.
- Effect on schedule
- Even “none” is worth writing down. If the change adds days, now is the time to say so.
- Customer approval
- A signature is best. If the customer agrees by text, email or phone instead, record how and when, and keep the message.
- Office use
- Where the change was billed. It closes the loop, so nothing is billed twice or missed.
A filled-in example
A customer asks for a paver edge along the front bed while the crew is on site. The crew lead fills in the form, prices it from the company’s rates, and the customer approves it by text. Names, numbers and prices are made up.
Change order
Example Landscape Co. · (555) 010-0142
- No.
- CO-014
- Date
- 2026-10-14
- Customer
- J. Williams
- Property address
- 12 Maple Crescent
- Phone or email
- (555) 010-0187
- Original estimate or contract no.
- EST-2026-031
- Crew lead
- Mike
- Prepared by
- Mike
The change: what is added, removed or different
Add a paver edge along the front bed (32 stones), set on screenings over landscape fabric.
Why
☒ Customer request, asked on site
| Qty | Unit | Description | Rate | Amount |
|---|---|---|---|---|
| Crew hours | ||||
| 4 | hr | Crew lead | $65.00 | $260.00 |
| 4 | hr | Crew member | $50.00 | $200.00 |
| Materials | ||||
| 32 | ea | Paver edge stone, straight | $9.50 | $304.00 |
| 0.5 | yd | Limestone screenings | $70.00 | $35.00 |
| 1 | roll | Landscape fabric, 3 × 50 ft | $28.00 | $28.00 |
| Equipment, disposal and other | ||||
| 1 | load | Disposal of removed sod | $40.00 | $40.00 |
| Subtotal | $867.00 | |||
| Tax (13%) | $112.71 | |||
| Total for this change | $979.71 | |||
Effect on schedule:None, done the same day
Customer approval
I approve the change described above and the added cost.
J. Williams
Customer name
Approved by text, 1:42 PM (saved)
Signature
2026-10-14
Date
Not signed on site? Record how it was approved: ☐ Text ☐ Email ☐ Phone ☐ In person, and keep the message.
Office use: added to invoice no. ________ on ________ by ____
Free template from scrivell.com
Tips for using it on site
01Keep a pad in every truck
A change order nobody can find on site doesn’t get written. Print a stack, or keep the PDF on the crew lead’s phone.
02Write it before the work, when you can
Agreeing the price first is easier than collecting it afterwards. If you can’t price it on the spot, agree the rates and write down the quantities as you go.
03One change per form
Two changes on one sheet are hard to approve, bill or dispute separately.
04Photograph the signed form
Send the photo to the office the same day, and give the customer a copy.
05Bill it while it’s fresh
The office adds each change order to the invoice and fills in the office-use line. Once a week, check for any numbers that never reached billing.
Where Scrivell fits
A paper form works when someone remembers to fill it in. Often the details are said out loud instead, in a voice memo or a text to the office. Scrivell catches those. Crews text a dedicated Scrivell number, and a message about extra work becomes a change order record with the work added, the materials and quantities, the price if one was stated, and whether the customer agreed. Hours become labour logs, and a receipt photo becomes a materials purchase.
What the office sees · example
Williams backyard
Voice memo · 1:38 PM
“Williams place. Customer wants a paver edge along the front bed, thirty-two stones. Homeowner okayed it.”
Change order · Williams
- + Paver edge, front bed
- 32 edge stones
- Customer agreed
The office confirms or edits the record, then uses it to fill in the change order or the invoice. Scrivell doesn’t produce this form, collect signatures or send invoices: it makes sure the change reaches the office with the details intact, and flags it when it isn’t clear the customer agreed.
See how it works for landscaping companies.